CBD hotmix road resurfacing planned

The Whakatāne District Council’s Transportation group advises that hotmix road resurfacing work will temporarily affect access at a number of locations in the Whakatāne CBD area from the middle of November through to January 2019.

Transportation Manager Martin Taylor says contractor Fulton Hogan Ltd will make every effort to complete the resurfacing work with the least possible disruption to nearby businesses and properties, and advisory letters will be delivered in each area, several days prior to work commencing.

"The table below shows the locations and expected days and times the resurfacing work will be undertaken," he says. "However, progress with the work programme is weather-dependent, so it's possible the timing could change, or that a scheduled closure could run for longer than the time advised. If that is the case, we'll let people know via media and social media messaging.

"Work at these sites will be undertaken at night, to minimise traffic disruption, and road closures and well-signed detours will apply."

Mr Taylor says road closures and well-signed diversions will apply at all other work-sites.

Hotmix Resurfacing Programme
Resurfacing WorksDates*Time
Fishing Club car park entrance - Commercial HotelCompleted 
   Quart House crossing Completed
 
Commerce Street roundabout - Paper Plus crossingCompleted 
The Strand: Wally Sutherland car yard - 1XX roundaboutCompleted
 
McAlister/Pyne Street roundaboutCompleted 
Boon Street: Richardson Street - Pyne StreetCompleted
 

King Street: James Street roundabout  - Bakehouse Roundabout

31st Jan / 1 Feb7 pm - 6 am
 
Domain Road: Commerce Street - McAlister Street27/28/29/30/31 January6 pm - 6 am

 * Note: Dates are subject to change, depending on weather conditions.